"While you're here, can you also..." might be the most expensive phrase in contracting. Scope creep—work that expands beyond the original agreement—is one of the fastest ways to turn a profitable job into a money-loser. Change orders are your protection.
What Is a Change Order?
A change order is a written document that modifies the original scope, cost, or timeline of a contract. It's signed by both parties before the additional work begins. Think of it as an amendment to your original agreement.
Change orders protect both you and the customer:
- For you: Documentation that extra work was requested and approved, with agreed pricing
- For the customer: Clear understanding of additional costs before they're incurred
When to Use a Change Order
Issue a change order whenever there's a change to:
Scope of Work
- Customer requests additional work ("Can you also replace the faucet while you're under the sink?")
- Customer wants something different than originally specified ("I changed my mind about the tile color")
- Work needs to be removed from the original scope
Unforeseen Conditions
- Hidden damage discovered during demolition (rot, mold, structural issues)
- Code violations that need correction
- Different conditions than originally assessed ("The wall is concrete, not drywall")
Material Changes
- Customer upgrades to more expensive materials
- Originally specified materials are unavailable and substitutes cost more
- Price increases on materials between estimate and work
Timeline Changes
- Customer delays that affect your schedule
- Rush requests that require overtime or schedule changes
What Should Be in a Change Order?
Every change order should include:
1. Reference Information
- Change order number (CO-001, CO-002, etc.)
- Date
- Reference to original contract/estimate
- Customer name and project address
2. Description of Change
Clearly describe what's being changed:
- What work is being added, removed, or modified
- Why the change is necessary (customer request, unforeseen conditions, etc.)
- How it differs from the original scope
3. Cost Impact
Break down the financial impact:
- Additional labor costs
- Additional material costs
- Credit for removed work (if applicable)
- Net change to contract amount
- New total contract amount
4. Schedule Impact
If the change affects timing:
- Additional days required
- New estimated completion date
- Reason for delay (material lead time, additional work hours, etc.)
5. Signatures
- Customer signature and date
- Your signature and date
- Statement that signing authorizes the work and additional cost
How to Present Change Orders
Presenting a change order can feel awkward, especially mid-project. Here's how to handle it professionally:
Be Proactive, Not Reactive
As soon as you identify a change, stop and discuss it. Don't do the extra work and then surprise the customer with a bigger bill. The conversation should happen before any additional work begins.
Explain the "Why"
Customers are more understanding when they know why something costs extra:
- "The original estimate was for standard drywall. The cement board you need for the shower area takes longer to install and costs more."
- "When we opened up the wall, we found some rot that needs to be fixed before we can proceed safely."
Put It in Writing Before Proceeding
Never, ever do change order work based on a verbal agreement. Even if the customer says "just do it, I'll sign later"—don't. Too many contractors have done extra work only to have customers refuse to pay, claiming they never agreed to the cost.
Keep It Professional
Change orders aren't confrontational—they're how professional contractors operate. Present them matter-of-factly as a normal part of the construction process.
Handling "Can't You Just Include That?"
Sometimes customers expect small additions to be free. Here's how to handle common pushback:
"It's such a small thing."
Response: "I understand it seems small, but it does add time and materials. If I don't document it, I end up absorbing costs that weren't in the original price, and that's not sustainable for my business. I want to do great work for you at a fair price—and change orders help me do that."
"The last contractor didn't charge extra for stuff like this."
Response: "Every contractor runs their business differently. I document everything so there are no surprises for either of us at the end of the project."
"Just this once?"
Response: "I'd love to help, but if I make exceptions, I can't stay in business. I keep my prices fair by billing for the work I do. Would you like me to include this in a change order, or would you prefer we stick with the original scope?"
Common Change Order Mistakes
- Doing the work before getting the signature: Always get it signed first. Always.
- Vague descriptions: "Additional work per customer request" won't protect you in a dispute. Be specific.
- Not tracking cumulative changes: Keep a running total of change orders so both you and the customer know where the project stands.
- Forgetting schedule impact: Extra work usually means extra time. Document it.
- Being afraid to issue them: Change orders are professional and expected. Customers respect contractors who document properly.
Build Change Orders Into Your Process
The best way to handle change orders is to set expectations upfront:
- In your estimate: Include a note that any changes to scope will require a written change order.
- At project start: Remind the customer that you'll document any changes in writing before proceeding.
- During the project: When a customer asks for something extra, immediately say "I can definitely do that—let me write up a change order for the additional cost."
When customers know to expect change orders, they're not surprised when you present one.